Question: From the following information, draw the project network. Compute the early, late, and slack times for each activity. Identify the critical path. ( Hint: Draw
From the following information, draw the project network. Compute the early, late, and slack times for each activity. Identify the critical path. Hint: Draw the finishtostart relationships first.
tableIDDuration,tableFinishtoStartPredecessortableFinishtoStartLagtableAdditional LagRelationshipsLagANone,None,BANone,CAStartfinish C to DDBStartstart D to EFinishfinish D to EEBFinishfinish E to FFDNone,GCFinishfinish G to FHFNone,