Question: From the PFM case, the Data Warehouse project could be classified as a ( n ) _ _ _ _ _ _ _ _ _

From the PFM case, the Data Warehouse project could be classified as a(n)________________ IT project while the CRM could be classified as a(n)________________ IT project.
Group of answer choices
Revenue Enhancing; Cost Reduction
Revenue Enhancing; Mandatory
Cost Reduction; Revenue Enhancing
Technology Renewal; Revenue Enhancing
Mandatory; Cost Reduction