Question: Functional Point (FP) Estimation Method is said to be independent of computer language, capability and technology used. A contractor stipulates that a computer application is

Functional Point (FP) Estimation Method is said to be independent of computer language, capability and technology used. A contractor stipulates that a computer application is to be developed according to the present data in the table below. Before the system reaches the testing stage, the customer requests some changes which resulted to the addition of 100 FPs with changes to 55 existing FPs. After the acceptance testing stage, the customer asks for changes to some of the functions in the system amounting to 200 FPs and some new functions which amount to 125 additional FPs with deletion of 60 existing FPs.

Calculate the additional charge based on the present data.

FP feature

Pre-acceptance testing handover

Post-acceptance testing handover

Cost per FP

Rs 500

Rs 800

Additional FPs

100%

120%

Changed FPs

140%

175%

Deleted FPs

35%

60%

PLEASE HELP ON ABOVE QUESTION WITH COMPLETE EXPLANAITION

MODULE : SOFTWARE PROJECT MANAGEMENT

TOPIC : EVALUATION & ESTIMATION

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!