Question: fUsing the following project status chart, calculate PV, EV, etc. in the spaces provided. Then check your answers. Activity Day 1 Day 2 Day 3


\fUsing the following project status chart, calculate PV, EV, etc. in the spaces provided. Then check your answers. Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3 Side 1 -F Complete, spent $1,000 Side 2 S----F----PF Complete, spent $900 Side 3 S---- PS. PF 50% done, spent $600 Side 4 S---- PS--....- -PF 75% done, spent $600 Key S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish