Question: fUsing the following project status chart, calculate PV, EV, etc. in the spaces provided. Then check your answers. Activity Day 1 Day 2 Day 3

 \fUsing the following project status chart, calculate PV, EV, etc. inthe spaces provided. Then check your answers. Activity Day 1 Day 2Day 3 Day 4 Status End of Day 3 Side 1 -F

\fUsing the following project status chart, calculate PV, EV, etc. in the spaces provided. Then check your answers. Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3 Side 1 -F Complete, spent $1,000 Side 2 S----F----PF Complete, spent $900 Side 3 S---- PS. PF 50% done, spent $600 Side 4 S---- PS--....- -PF 75% done, spent $600 Key S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned FinishExercise The Fence #2 You have a project to build a new fence. The fence will form a square, as shown at right. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides were planned to be completed one after the other; however, circumstances changed on the project, and work on the sides was able to proceed in parallel. Assume therefore that the sides have a finish-to-finish relationship instead of a finish-to-start relationship, so more than one side can be worked on at the same time. Today is the end of day 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!