Question: g submissions until Monday, March 2 5 , Show instructions Question 8 ( 1 point ) A project manager is considering how to structure a

g submissions until Monday, March 25,
Show instructions
Question 8(1 point)
A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, which of the following structure would be the best choice?
a Projectized
b Balanced Matrix
Weak Matrix