Question: Gantt Charting The table below includes information about four jobs and three work centers. Assume that six hours is required to transfer a job from

Gantt Charting The table below includes
Gantt Charting The table below includes information about four jobs and three work centers. Assume that six hours is required to transfer a job from one work center to another (move time not including waiting time for busy machines). Sequence the jobs with a Gantt chart. Use the following priority order: 1, 2, 3, 4. Can you tell if any jobs will be late? Which ones? Can a simple reordering of job priorities alleviate the problem? Work center / Machine hours Due date (days) A/2,B/1, C/4 3 C/4, A/2 2 B/4, A/2 2 B/4, A/2, C/3 Job 2 3