Question: General Foundrys project crashing data are shown below. Develop a project network for this problem using AON. Crash this project to 13 weeks using CPM.

General Foundrys project crashing data are shown below. Develop a project network for this problem using AON. Crash this project to 13 weeks using CPM.

  1. Determine the ES, EF, LS, LF, and slack time for each activity. Also determine the total project completion time and the critical path(s).
  2. What is the final time for each activity after crashing?
  3. What is the crash cost per week per activity and the total cost of crashing?

TIME (WEEKS)

COST ($)

ACTIVITY

IMMEDIATE PREDECESSORS

NORMAL

CRASH

NORMAL

CRASH

A

2

1

22,000

23,000

B

3

1

30,000

34,000

C

A

2

1

26,000

27,000

D

B

3

2

48,000

49,000

E

C

4

2

56,000

58,000

F

C

3

2

30,000

30,500

G

D, E

5

2

80,000

83,000

H

F, G

2

1

16,000

19,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!