Your company was hired as a subcontractor for a client's Destiny project and awarded two main...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Your company was hired as a subcontractor for a client's "Destiny" project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2_2020". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So, a start date of 13, for example, means that work on the workpackage should start on work day 13 after the "Destiny" project's start. You have "progress to date" and "cost to date" data for both workpackages for the end of day 18 (see table). On day 19 you are asked to fill out the remaining columns, perform an Earned Value Analysis and comment on each of the workpackages' performances as well as on the overall performance of your project "P2_2020". Cost Code P2_2020.1.100 Name WorkPackage 1 ● WorkPackage P2_2020.1.200 Total for Project P2_2020 2 Start (Start of Day...) 44500 13 Budget ($) 98000 16 Finish (End of Day...) 19 22 Cost To Date ($) 62299 28983 Progress To Date (%) 100 65 Report Date (End of Day...) 18 18 BCWP ($) BCWS ($) ACWP ($) A) Finish the table above by filling in all of the missing values. (Use mathematical rounding and round to two decimal places. Don't include units.) B) For the following schedule questions, enter 0 if your answer is "on track", -1 if your answer is "behind schedule" or enter 1, if your answer is "ahead of schedule". • B1: What's your assessment of the Work Package 1? Is Work Package 1 on track (0), behind schedule (-1) or ahead of schedule (1)? Answer: • B2: What's your assessment of the Work Package 2? Is Work Package 2 on track (0), behind schedule (-1) or ahead of schedule (1)? Answer: • B3: What's your assessment of the project P2_2020 overall? Is the project on track (0), behind schedule (-1) or ahead of schedule (1)? Answer: C) For the following budget questions, enter 0 if your answer is "on budget", -1 if your answer is "over budget" or enter 1, if your answer is "under budget". • C1: What's your assessment of the Work Package 1? Is Work Package 1 on budget (0), over budget (-1) or under budget (1)? Answer: • C2: What's your assessment of the Work Package 2? Is Work Package 2 on budget (0), over budget (-1) or under budget (1)? Answer: C3: What's your assessment of the project P2_2020 overall? Is the project on budget (0), over budget (-1) or under budget (1)? Answer: SPI CPI Your company was hired as a subcontractor for a client's "Destiny" project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2_2020". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So, a start date of 13, for example, means that work on the workpackage should start on work day 13 after the "Destiny" project's start. You have "progress to date" and "cost to date" data for both workpackages for the end of day 18 (see table). On day 19 you are asked to fill out the remaining columns, perform an Earned Value Analysis and comment on each of the workpackages' performances as well as on the overall performance of your project "P2_2020". Cost Code P2_2020.1.100 Name WorkPackage 1 ● WorkPackage P2_2020.1.200 Total for Project P2_2020 2 Start (Start of Day...) 44500 13 Budget ($) 98000 16 Finish (End of Day...) 19 22 Cost To Date ($) 62299 28983 Progress To Date (%) 100 65 Report Date (End of Day...) 18 18 BCWP ($) BCWS ($) ACWP ($) A) Finish the table above by filling in all of the missing values. (Use mathematical rounding and round to two decimal places. Don't include units.) B) For the following schedule questions, enter 0 if your answer is "on track", -1 if your answer is "behind schedule" or enter 1, if your answer is "ahead of schedule". • B1: What's your assessment of the Work Package 1? Is Work Package 1 on track (0), behind schedule (-1) or ahead of schedule (1)? Answer: • B2: What's your assessment of the Work Package 2? Is Work Package 2 on track (0), behind schedule (-1) or ahead of schedule (1)? Answer: • B3: What's your assessment of the project P2_2020 overall? Is the project on track (0), behind schedule (-1) or ahead of schedule (1)? Answer: C) For the following budget questions, enter 0 if your answer is "on budget", -1 if your answer is "over budget" or enter 1, if your answer is "under budget". • C1: What's your assessment of the Work Package 1? Is Work Package 1 on budget (0), over budget (-1) or under budget (1)? Answer: • C2: What's your assessment of the Work Package 2? Is Work Package 2 on budget (0), over budget (-1) or under budget (1)? Answer: C3: What's your assessment of the project P2_2020 overall? Is the project on budget (0), over budget (-1) or under budget (1)? Answer: SPI CPI
Expert Answer:
Answer rating: 100% (QA)
WorkPackage 1 BCWP Budget x Actual Completion percentage Days 44500 x 100 445 BCWS Budget x Planned ... View the full answer
Related Book For
Advanced Accounting
ISBN: 9781260247824
14th Edition
Authors: Joe Ben Hoyle, Thomas Schaefer, Timothy Doupnik
Posted Date:
Students also viewed these accounting questions
-
An employee was hired as a CES Intern. He signed an agreement stating that one of the conditions of continued employment was either meeting or working toward completion of an educational requirement...
-
A woman was hired as a dental assistant at age 20 and worked for the same dentist for over ten years. The dentist said on a number of occasions that she was the best dental assistant he ever had....
-
The plaintiff, a female computer programmer, was hired as a Data Analyst with a salary of $46,000 per year. She had a bachelors degree in mathematics and nearly 7 years of programmer experience. She...
-
Pick a Nigerian brand that has been very successful competing against the bigger global brands in its product category. What are the elements of its strategy that have enabled it to achieve this...
-
Classify the following accounts into one of the following categories: a. Assets b. Liabilities c. Equity d. Revenue e. Expense f. Off-balance-sheet activities (1) Service fees charged on deposit...
-
Prior to getting involved in networking, its a good idea to prepare an elevator speech. This is a 30-second pitch that summarizes what you want people to know about you. You might think of yourself...
-
After returning from a skiing vacation in Vermont, Leslie Adel came down with Legionnaires Disease. He claimed it was from the water drunk at the ski resort and provided by Greensprings of Vermont...
-
A Del Hardware has four employees who are paid on an hourly basis plus time-and-a half for all hours worked in excess of 40 a week. Payroll data for the week ended March 15, 2010, are presentd below....
-
Research articles on Online Analytic Processing (OLAP) and Online Transaction Processing (OLTP). Next, compare and contrast the key similarities and differences between Online Analytical Processing...
-
Consider the hypothetical eutectic phase diagram for metals A and B, which is similar to that for the lead-tin system, Figure 9.8. Assume that (1) and phases exist at the A and B extremities of the...
-
A debtor must disclose some of the characteristics of its long term debt but most of it must be disclosed in the Notes To The Financial Statements rue False.
-
A broker is required to reconcile the trust accounts for all income and expenses. They must make sure that all the accounts have all the information available and that the accounts balance. How often...
-
The expected value, standard deviation of returns, and coefficient of variation for asset A are ________. (See table below.) Possible Outcomes Probability Returns (%) Pessimistic 0.25 5% Most Likely...
-
1)Grunewald Industries sells on terms of 3/10, net 50. Gross sales last year were $4,781,500 and accounts receivable averaged $589,500. Half of Grunewald's customers paid on the 10th day and took...
-
What would be the net present value after five years if you buy an espresso machine today that costs $1,590 and will save you $680 a year on Starcracks expenses? Assume an average return on your...
-
A 13-year, 6 percent coupon bond pays interest semiannually. The bond has a face value of $1,000. What is the percentage change in the price of this bond if the market yield to maturity rises to 5.7...
-
Listed below are selected items from Watson Products' Cost of Quality (COQ) report from last month: Category Amount Redo ps 760 equipment maintenance 1,259 product tests 891 Field Service Costs 630...
-
Establish identity. cos( + k) = (-1)k cos , k any integer
-
Parson Company acquired an 80 percent interest in Syber Company on January 1, 2020. Any portion of Sybers business fair value in excess of its corresponding book value was assigned to trademarks....
-
The E.N.D. partnership has the following capital balances as of the end of the current year: Pineda . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 230,000 Adams . . . . . . ....
-
A company must prepare IFRS financial statements for the first time on December 31, 2022. According to IFRS 1, what is the date of transition to IFRS for this company? a. January 1, 2020 b. January...
-
What is the difference between internal and external audiences?
-
Like most major corporations, the U.S. Census Bureau has multiple, conflicting audiences, among them the president, Congress, press, state governments, citizens (both as providers and users of data),...
-
Listed here are several things an organization might like its employees to do: 1. Write fewer emails. 2. Volunteer at a local food pantry. 3. Volunteer to recruit interns at a job fair. 4. Attend...
Study smarter with the SolutionInn App