Given a SOG that measures 48 feet X 125 feet X 7 inches thick. How much would
Fantastic news! We've Found the answer you've been seeking!
Question:
Given a SOG that measures 48 feet X 125 feet X 7 inches thick. How much would you bid to place and finish this SOG. Please use the following information to do this estimate. Formed on all four sides 2x8 forms and necessary form support would be $1.05 cents UF This slab needs a 4" gravel base. Gravel is 510.00 a CY Cost of concrete 5117.50 per Cubic Yard. This includes all necessary admixtures and fiber Kure-N-Seal per 5 gal. Coverage is 300 SF per Gallon Cost per 5 Gallon $154.00. Only requires one coat. Labor to form, place finish, apply sealer, and saw cut is $5.85 SF Add 5% waste to the concrete and gravel and round up to the next cubic Yard, not the labor Use 76 for sales tax on al materials for this bid Finally add 12% markup to your final answer.