Question: Given activities and their corresponding time (weeks). Predecessor Activity A B D E F G A B,C D AE F Duration (weeks) 4 3 5

Given activities and their corresponding time

Given activities and their corresponding time (weeks). Predecessor Activity A B D E F G A B,C D AE F Duration (weeks) 4 3 5 6 2 4 2 a. Please calculate the project completion time. Make sure you show ES/EF and LS/LF for each activity on AON network. b. What is the critical path