Question: Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 3, and 9 days respectively, compute the PERT time for this activity

Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 3, and 9 days respectively, compute the PERT time for this activity