Question: Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity. A)
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
E) None of the above