Question: Given is a CPM project network diagram as shown below. a ) The Project Completion time = 1 3 ? days. b ) The Earliest

Given is a CPM project network diagram as shown below.
a) The Project Completion time =13? days.
b) The Earliest Start time, ES, of Activity G=7? days.
c) The Latest Finish time, LF, of Activity C=4? days.
d) The critical activities are = CEFGH (ex. Fill in the answer as: ABCD)?
Blank
Blank 2
Blank 4 ACEFGH