Question: Given is a CPM project network diagram as shown below. a) The Project Completion time =25 days. b) The Earliest Start time, ES, of Activity

Given is a CPM project network diagram as shown

Given is a CPM project network diagram as shown below. a) The Project Completion time =25 days. b) The Earliest Start time, ES, of Activity G=13 days. c) The Latest Finish time, LF, of Acitivity C=11 days. d) The critical activities are =ACEGH (ex. Fill in answer as: ABCD)