Question: Given is a CPM project network diagram as shown below. a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of
Given is a CPM project network diagram as shown below.

a) The Project Completion time = ____ days.
b) The Earliest Start time, ES, of Activity G =____ days.
c) The Latest Finish time, LF, of Activity C =____ days.
d) The critical activities are = ___(ex. Fill in the answer as: ABCD)
*** THERE SHOUD BE 3 ANSWERS. PLEASE ANSWER CAREFULLY
\begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|l|} \hline Activit y & Start & A & B & C & D & E & F & G & H & End \\ \hline day & 0 & 3 & 3 & 6 & 5 & 6 & 4 & 2 & 5 & 0 \\ \hline \end{tabular}Step by Step Solution