Question: Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? a. The project is

Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? a. The project is over budget and ahead of schedule b. The project is under budget and ahead of schedule c. The project is under budget and behind schedule d. The project is over budget and behind schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!