Question: Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? a. The project is

Given PV (BCWS) equals $1,500,000; EV (BCWP)

Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? a. The project is over budget and ahead of schedule b. The project is under budget and ahead of schedule c. The project is under budget and behind schedule d. The project is over budget and behind schedule