Question: Given the activities described by the following table: table [ [ Activity , table [ [ Expected ] , [ Time ] ]

Given the activities described by the following table:
\table[[Activity,\table[[Expected],[Time]],\table[[STD of],[Time],[Estimate]],\table[[Immediate],[Predecessor],[(s)]]],[a,7,2,-],[b,3,1,a],[c,9,3,a],[d,4,1,b,c],[e,5,1,b,c],[f,8,2,e],[g,8,1,d,f],[h,6,2,g]]
a. What is the project completion time?
b. What is the project standard deviation?
c. Find the probability that the project will take more than 49 time periods to complete?
 Given the activities described by the following table: \table[[Activity,\table[[Expected],[Time]],\table[[STD of],[Time],[Estimate]],\table[[Immediate],[Predecessor],[(s)]]],[a,7,2,-],[b,3,1,a],[c,9,3,a],[d,4,1,b,c],[e,5,1,b,c],[f,8,2,e],[g,8,1,d,f],[h,6,2,g]] a.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!