Question: Given the data above, if we crashed the schedule eleven weeks, how much would the new project cost? Given the following project data and diagram

Given the data above, if we crashed the schedule eleven weeks, how much would the new project cost?
Given the following project data and diagram that represents every activity fully crashed:
\table[[Activity,Normal Time (Weeks),Normal Cost,Crash Time (Weeks),Crash Cost],[A,9,$4,400,6,$6,200
 Given the data above, if we crashed the schedule eleven weeks,