Question: Given the following project data and diagram that represents every activity fully crashed : Activity Normal Time (Weeks) Normal Cost Crash Time (Weeks) Crash Cost
Given the following project data and diagram that represents every activity fully crashed:
| Activity | Normal Time (Weeks) | Normal Cost | Crash Time (Weeks) | Crash Cost |
| A | 9 | $4,400 | 6 | $6,200 |
| B | 6 | $5,200 | 3 | $5,800 |
| C | 3 | $4,500 | 3 | $4,500 |
| D | 4 | $4,000 | 2 | $6,000 |
| E | 6 | $4,200 | 3 | $6,600 |
| F | 8 | $3,700 | 4 | $5,700 |
| G | 7 | $4,000 | 5 | $6,000 |
| H | 7 | $6,000 | 5 | $7,500 |

Can any money be saved in the diagram above without sacrificing the minimum project completion time?
What is the optimal project cost for a 19-week completion schedule?
19 A(6), B(3), G(5), H(5) C(3),E(3),F(4), H(5) 15 C(3),D(2).F(4), H(5) 14Step by Step Solution