Question: Given the following project data and diagram that represents every activity fully crashed : Activity Normal Time (Weeks) Normal Cost Crash Time (Weeks) Crash Cost

Given the following project data and diagram that represents every activity fully crashed:

Activity

Normal Time (Weeks)

Normal Cost

Crash Time (Weeks)

Crash Cost

A

9

$4,400

6

$6,200

B

6

$5,200

3

$5,800

C

3

$4,500

3

$4,500

D

4

$4,000

2

$6,000

E

6

$4,200

3

$6,600

F

8

$3,700

4

$5,700

G

7

$4,000

5

$6,000

H

7

$6,000

5

$7,500

Given the following project data and diagram that

Can any money be saved in the diagram above without sacrificing the minimum project completion time?

What is the optimal project cost for a 19-week completion schedule?

19 A(6), B(3), G(5), H(5) C(3),E(3),F(4), H(5) 15 C(3),D(2).F(4), H(5) 14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!