Question: Given the data and information that follow, compute the total direct cost for each project duration. The indirect costs for each project duration are shown
Given the data and information that follow, compute the total direct cost for each project duration. The indirect costs for each project duration are shown in the following table:
| Time units | Indirect costs |
| 15 | 90 |
| 14 | 70 |
| 13 | 50 |
| 12 | 40 |
| 11 | 30 |
| Activity | Crash cost | Maximum | ||
| ID | (Slope) | Crash Time | Normal time | Normal cost |
| A | 30 | 1 | 5 | 50 |
| B | 60 | 2 | 3 | 60 |
| C | 0 | 0 | 4 | 70 |
| D | 10 | 1 | 2 | 50 |
| E | 60 | 3 | 5 | 100 |
| F | 100 | 1 | 2 | 90 |
| G | 30 | 1 | 5 | 50 |
| H | 0 | 0 | 2 | 60 |
| I | 200 | 1 | 3 | 200 |
| Total direct normal costs | $730 | |||
To compress from time period 15 to time 14, crash the following activity(s):
check all that apply
A
B
C
D
E
F
G
H
I
To compress from time period 14 to time 13, crash the following activity(s):
check all that apply 2
A
B
C
D
E
F
G
H
I
To compress from time period 13 to time 12, crash the following activity(s):
check all that apply 3
A
B
C
D
E
F
G
H
I
What is the crash point of the network?
Time Period, _____
Total Cost, _____
What is the optimum cost-time schedule for the project? _____ Time Periods
What is this cost?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
