Question: Given the data and information that follow, compute the total direct cost for each project duration. The indirect costs for each project duration are shown

Given the data and information that follow, compute the total direct cost for each project duration. The indirect costs for each project duration are shown in the following table:

Time units Indirect costs
15 90
14 70
13 50
12 40
11 30

Activity Crash cost Maximum
ID (Slope) Crash Time Normal time Normal cost
A 30 1 5 50
B 60 2 3 60
C 0 0 4 70
D 10 1 2 50
E 60 3 5 100
F 100 1 2 90
G 30 1 5 50
H 0 0 2 60
I 200 1 3 200
Total direct normal costs $730

To compress from time period 15 to time 14, crash the following activity(s):

check all that apply

A

B

C

D

E

F

G

H

I

To compress from time period 14 to time 13, crash the following activity(s):

check all that apply 2

A

B

C

D

E

F

G

H

I

To compress from time period 13 to time 12, crash the following activity(s):

check all that apply 3

A

B

C

D

E

F

G

H

I

What is the crash point of the network?

Time Period, _____

Total Cost, _____

What is the optimum cost-time schedule for the project? _____ Time Periods

What is this cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!