Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration's are,

Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration's are, LE 90 (15 days), LE 70 (14 days), LE 50 (13 days), LE 40 (12 days), and LE 30 (11 days), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Duration (days) Activity Predecessors Normal Cost Normal Cost Slope (LE/day) 20 Crash A 5 4 50 B 3 1 60 60 A 4 4 0 70 D A 2 1 10 50 E B. 15 100 2 1 60 100 F C 2 5 90 50 G D 4 30 H E 2 40 60 F,G,H 3 2 200 200
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
