Question: Given the data below, using the SPT heuristic sequencing rule, determine the completion date and tardiness for each job as well as the average completion

Given the data below, using the SPT heuristicGiven the data below, using the SPT heuristic

Given the data below, using the SPT heuristic sequencing rule, determine the completion date and tardiness for each job as well as the average completion time and average tardiness for all four jobs. Which of the following statements is true? Job Processing time (days) Due date (in days) A 10 10 B 5 8 15 25 D 8 15 The average completion time is 6.5 The tardiness for Job A is 12 days The average tardiness is 19.75 Jobs B and D will have no tardiness