Question: Given the data shown below, use = 0.4 and = 0.5 to create a trend enhanced smoothing based forecast for period 2 (FIT 2 ).
Given the data shown below, use = 0.4 and = 0.5 to create a trend enhanced smoothing based forecast for period 2 (FIT2). Assume that FIT1 = 27 and T1 = 2.
| Given the data shown below, use = 0.4 and = 0.5 to create a trend enhanced smoothing based forecast for period 2 (FIT2). Assume that FIT1 = 27 and T1 = 2.
Group of answer choices 33.80 37.52 38.46 36.88 | |||||||||||||||||||||||||||||