Question: Given the following activities and predecessors, draw an AON / PDM network diagram and include Earliest Start, Earliest Finish, Latest Start, Latest Finish, Slack Time,

Given the following activities and predecessors, draw an AON/PDM network diagram
and include Earliest Start, Earliest Finish, Latest Start, Latest Finish, Slack Time, and
Duration for each Activity on the diagram. PERT estimating must be used for activity
duration - apply standard rounding to the nearest whole number (no decimals). Also
identify the critical path activities.
 Given the following activities and predecessors, draw an AON/PDM network diagram