Question: Given the following activity network: ( 3 activities A 1 , A 2 , & A 3 ; arrows point from A 1 to A

Given the following activity network: (3 activities A1, A2, & A3; arrows point from A1 to A2 & A1 to A3)
Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability. What is the project completion time estimate considering all scenarios?
Group of answer choices
9 weeks
10 weeks
12 weeks
13.5 weeks