Question: Given the following activity network: A2 A1 A3 Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 3 weeks with a 50%

Given the following activity network: A2 A1 A3

Given the following activity network: A2 A1 A3 Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 3 weeks with a 50% probability and 9 weeks with a 50% probability. What is the expected project completion time? 14