Question: Given the following activity network: Activity A 1 takes 5 weeks, A 2 takes 8 weeks, and A 3 takes 3 weeks. What is the
Given the following activity network:
Activity A takes weeks, A takes weeks, and A takes weeks. What is the earliest start time of A weeks round to the nearest integer