Question: Given the following activity network: image Activity A 1 takes 5 weeks, A 2 takes 8 weeks, and A 3 takes 2 weeks. What is

Given the following activity network:
image
Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the slack of A3?
8 weeks
6 weeks
4 weeks
0 weeks