Question: Given the following assumptions, develop a cost estimate (Labor only) that integrates all of the cost elements into a final bid price to the customer.
Given the following assumptions, develop a cost estimate (Labor only) that integrates all of the cost elements into a final bid price to the customer. What is the total cost for the project? How long will the project take to complete?
Function points in the project: 232
Software engineers assigned to this team: 5
Function point productivity per software engineer: 5 per month
Workdays per typical month: 22
Productive hours per typical workday: 8
Gross hourly wage rate per software engineer (does not include fringe benefits): $50 per hour
Overhead (fringe benefit, other direct overhead) rate 35%
G&A rate: 11.5%
Proposed Profit: 10%
What is the total cost to the customer for the project?