Question: Given the following assumptions, develop a cost estimate that integrates all of the cost elements into a final bid price to the customer. Function points

Given the following assumptions, develop a cost estimate that integrates all of the cost elements into a final bid price to the customer. Function points in the project: 234 Software engineers assigned to this team: 4 Function point productivity per software engineer: 5 per month Workdays per typical month: 22 Productive hours per typical workday: 8 Gross hourly wage rate per software engineer (does not include fringe benefits): $50 per hour Overhead (fringe benefit, other direct overhead) rate: 32% G&A rate: 11.5% Proposed profit: 10%.