Question: Given the following assumptions, develop a cost estimate that integrates all of the cost elements into a final bid price to the customer. Function points
Given the following assumptions, develop a cost estimate that integrates all of the cost elements into a final bid price to the customer.
Function points in the project: 234
Software engineers assigned to this team: 4
Function point productivity per software engineer: 5
per month Workdays per typical month: 22
Productive hours per typical workday: 8
Gross hourly wage rate per software engineer (does not include fringe benefits): $50 per hour
Overhead (fringe benefit, other direct overhead) rate: 32%
G&A rate: 11.5%
Proposed profit: 10%
What is the total cost for the project?
$606,146.11
$666,760.72
$692,245.50
$677,654.24