Question: Given the following data, compute the production standard (pieces per hour), the standard labor cost per 100 pieces, and the standard hours per 100
Given the following data, compute the production standard (pieces per hour), the standard labor cost per 100 pieces, and the standard hours per 100 pieces. The allowances are 4% for fatigue, 8% for unavoidable delays, and 8% for personal needs. The operator is paid $5 per hour. Performance rating = 105%. Element 1 2 3 4 Reading (minutes) 2 3 4 1 0.020 0.010 0.009 0.012 0.002 0.030 0.004 0.004 0.100 0.110 0.009 0.050 0.205 0.195 0.200 0.210
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
1 Add up the reading times for each element Element 1 0020 0010 0009 0012 0051 Element 2 0002 0030 ... View full answer