Question: Given the following data, develop MRP plans for items C, D, E and F.MPS start for end items: The following table shows the MPS start

Given the following data, develop MRP plans for items C, D, E and F.MPS start for end items: The following table shows the MPS start information for two end items: item A and B. For example, we have a plan to start producing 70 units of end item A in week 2.

End item Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

A 30(week 1) 70 (week 2) 80 (week 6)

B 60 (week 4) 110 (week 6)

Bill of materials:-

End item A is made of 1 unit of item C and 1 unit of item D.

Item D is made of 2 units of item E and 2 units of item F.

End item B is made of 1 unit of item C and 2 units of item F

Item Lead Time weeks Lot sizing Saftey stock req On hand inventory Scheduled receipts

C [2 weeks] [L4L] [0] [60] [80 IN WEEK1]

D [1 week] [L4L] [0] [80] [NONE]

E [1 week] [FOQ (200)] [0] [90] [NONE]

F [1 week] [FOQ (100)] [10] [30] [200 in week 1]

I need help finding GR, SR, PAB, PR, AND POR FOR ITEMS,C, E D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!