Question: Given the following data for a project network: Times (weeks) Activity Optimistic Most Likely Pessimistic A 9 15 21 B 13 21 23 C 6
Given the following data for a project network:
Times (weeks)
Activity Optimistic Most Likely Pessimistic
A 9 15 21
B 13 21 23
C 6 9 18
D 23 35 47
E 19 26 27
F 23 29 41
G 14 20 26
H 2 5 8
What are the estimated standard deviations (in weeks) in the times for activity H?
a. 1.5
b. 1.67
c. 0.25
d. 1
e. None of the above