Question: Question Completion Status: Activity A B D E F G H Start Node 1 1 2 2 3 4 5 6 Finish Node 2 3

Question Completion Status: Activity A B D E F G
Question Completion Status: Activity A B D E F G H Start Node 1 1 2 2 3 4 5 6 Finish Node 2 3 4 5. 5 6 6. 7 Duration Estimate (Days) Optimistic Most Likely Pessimistic 15 21 13 21 23 6 9 18 23 35 47 19 26 27 23 29 41 20 26 2 5 8 0 14 What is the estimated expected (mean) time (in weeks) for project completion? 35 75 115 O 170

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock