Given the following data for Project M calculate the NPV of the project. C 0 C 1
Fantastic news! We've Found the answer you've been seeking!
Question:
Given the following data for Project M calculate the NPV of the project.
C0 | C1 | C2 | |
Cash flow in real terms: | −200 | 150 | 120 |
Real discount rate = 5% | |||
Nominal discount rate = 10% | |||