Question: Given the following information and MRP table for part A; The planned-order release in week 4 will be: 1-There will be a previously arranged scheduled

Given the following information and MRP table for part A; The planned-order release in week 4 will be: 1-There will be a previously arranged scheduled receipt of 400 units of part A at the beginning of week 2. 2- Manufacturing lead time is two weeks. 3- This part must be ordered in multiples of 100 units. 4-Currently, there are 700 on-hand inventory.

Parts/ Week 1 2 3 4 5 6
Part: A Lt=2 week Lot size: Q=100 Projected on hand= 700 Open order in week 2= 400 Gross Requirements 500 320 540 610 800 920
Scheduled receipts 400
Projected on-hand 700
Net requirements
Planned-order receipts
Planned-order releases

Multiple Choice

  • 890

  • 800

  • 300

  • 900

  • 600

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!