Question: Given the following information and MRP table for part A; The planned-order release in week 4 will be: 1-There will be a previously arranged scheduled
Given the following information and MRP table for part A; The planned-order release in week 4 will be: 1-There will be a previously arranged scheduled receipt of 400 units of part A at the beginning of week 2. 2- Manufacturing lead time is two weeks. 3- This part must be ordered in multiples of 100 units. 4-Currently, there are 700 on-hand inventory.
| Parts/ Week | 1 | 2 | 3 | 4 | 5 | 6 | |
| Part: A Lt=2 week Lot size: Q=100 Projected on hand= 700 Open order in week 2= 400 | Gross Requirements | 500 | 320 | 540 | 610 | 800 | 920 |
| Scheduled receipts | 400 | ||||||
| Projected on-hand | 700 | ||||||
| Net requirements | |||||||
| Planned-order receipts | |||||||
| Planned-order releases | |||||||
Multiple Choice
-
890
-
800
-
300
-
900
-
600
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock