Question: Given the following information and MRP table for part A; The planned-order release in weak 4 will be: 1-There will be a previoksly arranged scheduled
Given the following information and MRP table for part A; The planned-order release in weak 4 will be: 1-There will be a previoksly arranged scheduled receipt of 400 units of part A at the beginning of weok 2 . 2- Manufacturing lead time is two weeks. 3- This part must be ordered in multiples of 100 units. 4-Currently, there are 700 on-hand inventory
Step by Step Solution
There are 3 Steps involved in it