Question: Given the following information and MRP table for part E; The net requirement in week 7 will be: 1-Currently, there are 120 on-hand inventory. 2-There
Given the following information and MRP table for part E; The net requirement in week 7 will be: 1-Currently, there are 120 on-hand inventory. 2-There will be a previously arranged scheduled receipt of 300 units of part E at the beginning of week 3. 3- This part must be ordered in multiples of 100 units. 4- Lead time is one week. Part/ Week 1 2 3 4 5 6 7 Part: E Lt=1 week Lot size: Q=100 Projected on hand= 120 Open order in week 3= 300 Gross Requirements 100 280 340 500 380 720 200 Scheduled receipts 300 Projected on-hand 120 Net requirements Planned-order receipts Planned-order releases