Question: Given the following information and MRP table for part E; The net requirement in week 7 will be: 1-Currently, there are 120 on-hand inventory. 2-There

Given the following information and MRP table for

Given the following information and MRP table for part E; The net requirement in week 7 will be: 1-Currently, there are 120 on-hand inventory. 2-There will be a previously arranged scheduled receipt of 300 units of part E at the beginning of week 3 . 3- This part must be ordered in multiples of 100 units. 4- Lead time is one week. Multiple Choice 300 0 250 340 120