Question: Given the following information develop the time-phased project budget. You may need to use Microsoft Excel for this exercise. You can also refer to the
Given the following information develop the time-phased project budget. You may need to use Microsoft Excel for this exercise. You can also refer to the example provided in the "Baseline Budget Problem with Solution" file.
ID Predecessor Duration Budget
A None 3 weeks $30.000 B A 2 weeks $35.000 C A 1 week $7.000 D A 3 weeks $40.000 E B,C,D 3 weeks $21.000 Costs as you expect them to occur (weekly spending) Total A $8.000 $12.000 $10.000 $30.000 B $20.000 $15.000 $35.000 C $7.000 $7.000 D $20.000 $10.000 $10.000 $40.000 E $10.000 $11.000 $21.000