Question: Given the following information for an AOA network: Immediate table [ [ Activity , Duration ( days ) , Predecessor ( s ) ]
Given the following information for an AOA network:
Immediate
tableActivityDuration daysPredecessorsAB DBNoneCB DDNone
How many noncritical activityactivities is are there in this AOA?
Keep your own AOA graph.
Select one:
a There are three noncritical activities.
b There is only one noncritical activity.
c There are two noncritical activities.
d There are four noncritical activities.