Question: Given the following information for an AOA network: Immediate Activity A B C D Duration ( days ) 9 2 8 7 Predecessor ( s
Given the following information for an AOA network:
Immediate
Activity
A
B
C
D
Duration days
Predecessors
B C D
None
None
None
How many dummy arcs is are there in this AOA network?
Keep your own AOA graph.
Select one:
a two dummy arcs
b no dummy arc
c one dummy arc
d four dummy arcs
e three dummy arcs
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock