Question: Given the following information, please answer question 5 to question 8 . Activity Immediate Predecessors Completion Time ( Weeks ) A N / A 2

Given the following information, please answer question 5 to question 8. Activity Immediate Predecessors Completion Time (Weeks) A N/A 2 B A 3 C A 4 D B 1 E B,C 5 F D 6 G E 2 H E 3 Q5. What are the latest start and the latest finish of activity E? Group of answer choices 16,2111,166,118,13. What is the total project completion time?
Group of answer choices
11
14
12
13