Question: Given the following information, please answer question 9 ~ 1 2 Hint: p ( 0 < z < 1 . 6 4 5 ) =

Given the following information, please answer question 9~12
Hint: p(0< z <1.645)=0.45
Activity
Immediate
Predecessors
Completion Time (Weeks)
Optimistic
Most Likely
Pessimistic
A
N/A
1
2
3
B
A
2
4
6
C
A
2
5
8
D
A
1
1
1
E
B, C
2
3
4
F
D
1
2
3
Q9. What is the probability the project will be completed in 8 weeks?
Group of answer choices
0.0212
0.0351
0.0451
0.0514
Flag question: Question 10
Question 105 pts
What is the probability the project will be longer than 9.5 weeks?
Group of answer choices
0.2054
0.7054
0.1736
0.6736
Flag question: Question 11
Question 115 pts
What is the 90% confidence interval of the total project completion time?
Group of answer choices
6~13
8~12
7~10
5~8
Flag question: Question 12
Question 125 pts
Give a time within which you can be 95% sure of completing the project.
Group of answer choices
14.15
10.25
8.17
11.82

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!