Question: Given the following information, please answer question 5 to question 8 Activity Immediate Completion Predecessors Time (Weeks) A N/A 2 B A 3 C A




Given the following information, please answer question 5 to question 8 Activity Immediate Completion Predecessors Time (Weeks) A N/A 2 B A 3 C A 4 D B E B.C 5 F D 6 G E 2 H E 3 Q5. What are the latest start and the latest finish of activity E?Q5. What are the latest start and the latest finish of activity E? O 11,16 O 16,21 O 8,13 O 6, 11