Question: Given the following information, please answer question 9 ~ 1 2 Hint: p ( 0 < z < 1 . 6 4 5 ) =

Given the following information, please answer question 9~12
Hint: p(0< z <1.645)=0.45
Activity
Immediate
Predecessors
Completion Time (Weeks)
Optimistic
Most Likely
Pessimistic
A
N/A
1
2
3
B
A
2
4
6
C
A
2
5
8
D
A
1
1
1
E
B, C
2
3
4
F
D
1
2
3
Q9. What is the probability the project will be completed in 8 weeks?
Group of answer choices
0.0514
0.0212
0.0351
0.0451