Question: Given the following information regarding a project: Activity Duration Predeccors a 3 none b 1 none c 3 a d 4 a e 4 b
Given the following information regarding a project:
| Activity | Duration | Predeccors |
| a | 3 | none |
| b | 1 | none |
| c | 3 | a |
| d | 4 | a |
| e | 4 | b |
| f | 5 | b |
| g | 2 | c, e |
| h | 3 | f |
Which of the following is NOT a path in the network?
a) a-d
b) a-c-g
c) b-c-g
d) b-e-g
e) b-f-h
What is the critical path?
a) a-d
b) a-c-g
c) b-c-g
d) b-e-g
e) b-f-h
How long will it take to complete the project?
a) 6
b) 7
c) 8
d) 9
e) 10
What is the ES for activity g?
a) 1
b) 3
c) 5
d) 6
e) 7
What is the LF for activity a?
a) 0
b) 1
c) 3
d) 4
e) 5
What is the LF for activity b?
a) 1
b) 3
c) 5
d) 6
e) 7
What is the LF for activity d?
a) 1
b) 4
c) 6
d) 7
e) 9
What is the LF for activity g?
a) 6
b) 7
c) 8
d) 9
e) 10
What is the LF for activity h?
a) 6
b) 7
c) 8
d) 9
e) 10
What is the slack for activity b?
a) 0
b) 1
c) 2
d) 3
e) 4
Step by Step Solution