Question: Given the following information regarding a project: Activity Duration Predecessors a 4 None b 5 None c 5 a d 6 a e 5 b,c

Given the following information regarding a project:

Activity Duration Predecessors
a 4 None
b 5 None
c 5 a
d 6 a
e 5 b,c
f 4 d
g 5 e

What is the critical path? How long will it take to complete the project? What is the LS for activity a? What is the LF for activity f? What is the EF for activity g?